“We back up every night. Do we need a second site?” I’d ask the service owner to walk me through a morning without the application before we priced any infrastructure.
What happens between ten and noon?
Suppose the service stops at 10 a.m. Staff can take requests by hand for two hours. By noon the backlog would be too large to manage, so the owner sets a two-hour recovery time objective. That clock starts when service is lost. It includes the time it takes someone to notice, call the right people and decide to restore.
Then I’d ask about the person who submitted a request at 9:59 and already has a confirmation number. If we restore last night’s backup, how will staff know what they promised that person? The recovery point objective describes how far back the recovered data may be. The owner might tolerate re-entering fifteen minutes of drafts while requiring staff to account for every confirmed request. Those promises call for different ways to protect the records.
Rehearse the morning the service owner described
I’d give two test requests distinct confirmation numbers and keep them with the people playing the customers. Submit one shortly before the simulated outage. Have staff take the other by hand during it. In an isolated environment, have the on-call team recover the service using the backups, credentials and instructions that would still be available if the primary site were offline.
Record when staff can sign in, find the first request by its confirmation number and complete the next step through the dependent system. Have them enter the handwritten request and check that the receiving team sees it exactly once. Record separately how long it takes to clear the remaining manual work. Someone who runs the service should witness those checks and say when normal intake can resume.
Spend against the gap the rehearsal shows
Imagine staff can take new requests again in 70 minutes, but the 9:59 confirmation is missing. The team is inside its two-hour deadline and still owes someone work it can’t see. I’d first price a way to recover acknowledged requests, such as replaying a durable record kept outside the failed site. Then I’d repeat the same test.
If the records survive but provisioning replacement capacity takes three hours, I’d time a restore with the capacity prepared in advance. If losing the whole location still puts noon out of reach, I’d price a standby at a second site. Include connectivity, replication, who can switch traffic, and the cost of rehearsing the return to the primary site. Keep recoverable backups as well. An accidental deletion can reach both replicas.
I’d leave the owner with the agreed targets, the times we observed, the requests we could account for, and the cost of closing each remaining gap. If the existing setup meets both promises in the rehearsal, keeping it and scheduling the next exercise is a sound decision.